Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
3 98.26 5.1 5.19  
1 JALPAIGURI Jalpaiguri Division Rejuvanation of Riabari Tea Garden Area Piped Water Supply Scheme , SM/15103 Augmentation Construction of different components of Rejuvenation Of Riabari Tea Garden PWSS i.e. TW, Pump Houses, Water distribution Network, RISING MAIN FHTC etc. in connection with Jal Jeevan Mission at Block - Banarhat under Jalpaiguri Division, P.H.E.Dte. Assistant Engineer,HQ Junior Engineer ORD/000081/2023-2024 375/JD 30/05/2023 60 SAPTASWA SARKAR 71.77 0.00 0 50
2 JALPAIGURI Northern Mechanical Rejuvanation of Riabari Tea Garden Area Piped Water Supply Scheme , SM/15103 Augmentation New Service Connection Charge for REJU RIA BARI TEA GARDEN, T/W No. III, under BANARHAT CCC [APPLICATION NO. 4003333061 , Reference ID : 403157468] BILL/02006/2023-2024 BP/23-24/308 09/02/2024 WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED 15.73 0.00 0 0
3 JALPAIGURI Northern Mechanical Rejuvanation of Riabari Tea Garden Area Piped Water Supply Scheme , SM/15103 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVENATION OF RIABARI TEA GARDEN AREA PWSS, TW NO III in the district of Jalpaiguri under Northern Mechanical Division, PHE Dte. Driller-in-Charge Junior Engineer ORD/000668/2023-2024 1483/NMD 17/08/2023 30 KARMAKAR CONSTRUCTION 10.76 5.10 47.4 85
Total 98.25 5.10 5.19