Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
7 197.45 45.65 23.12  
1 JALPAIGURI Jalpaiguri Division REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Sinking of one No. tube well (250mm x 200mm) by Reverse Rotary Method of Drilling and Construction of Pump House (5.40m x 3.60m) and Iron Elimination Plant for direct boosting arrangement for Augmentation of Porapara Piped Water Supply Scheme under Jalpaiguri Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000069/2024-2025 988/JD 14/08/2024 120 SADHAN KARMAKAR 38.03 0.00 0 0
2 JALPAIGURI Jalpaiguri Division REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Construction of different components for Rejuvenation of Porapara PWSS I.e. TW, Pump Houses, Boundary wall IEP, Rising main etc. at Block - Jalpaiguri Sadar under Jalpaiguri Division, PHE Dte. Assistant Engineer Junior Engineer,Junior Engineer 2 ORD/000075/2023-2024 1003/JD 17/05/2023 45 B.M CONSTRUCTION 51.20 25.60 50 100
3 JALPAIGURI Jalpaiguri Division REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Emergency extension and reparing of pipe line to facilite FHTC at different location Pora Para Water Supply Scheme under Jalpaiguri Division, PHE Dte. Under JJM. Assistant Engineer Junior Engineer ORD/000448/2023-2024 1282/RWS 28/11/2023 20 B.M CONSTRUCTION 6.16 2.20 35.71 100
4 JALPAIGURI Jalpaiguri Division REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Engagement of Block Level Staff(Field Surveyor) through Implementation Agency for House hold survey (under ISA supervision) at Sadar block in Connection with JIM under Jalpaiguri Division, PHE Dte with in Jalpaiguri District. Assistant Engineer Junior Engineer ORD/000457/2023-2024 1290/RWS 29/11/2023 30 B.M CONSTRUCTION 3.89 1.95 50.13 100
5 JALPAIGURI Jalpaiguri Division REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Construction of different balance components of Rejuvenation of Porapara PWSS in connection with Jal Jeevan Mission at Block - Jalpaiguri Sadar under Jalpaiguri Division, P.H.E.Dte. Assistant Engineer Junior Engineer 2 ORD/000728/2023-2024 2494/JD 28/02/2024 30 SUKES BASU MAJUMDAR 74.69 0.00 0 0
6 JALPAIGURI Northern Mechanical REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVENATION OF PORAPARA PWSS, TW NO I in the district of Jalpaiguri under Northern Mechanical Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000236/2023-2024 1251/NMD 31/07/2023 30 TAPAN BISWAS 10.86 9.59 88.31 100
7 JALPAIGURI Northern Mechanical REJUVENATION OF PORA PARA PWSS , SM/15101 Augmentation Supply, installation, commissioning and trial operation of electro-mechanical components along with copper wound line voltage corrector for REJUVENATION OF PORAPARA PWSS, TW no V in the district of Jalpaiguri under Northern Mechanical Division, PHE Dte. Assistant Engineer Junior Engineer ORD/000327/2023-2024 1298/NMD 03/08/2023 30 M/S ANJALI ENTERPRISE 12.62 6.31 50 100
Total 197.45 45.65 23.12