Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
4 331.24 74.11 22.37  
1 DARJEELING Rangli Rangliot Neorakhola W/S & Mtc.Div. CHEGRA KHASMAHAL Piped Water Supply Scheme , SM/16141 New (CONTINUATION) COLLECTION OF WATER SAMPLES FROM DIFFERENT SOURCES UNDER KALIMPONG DISTRICT UNDER NEORAKHOLA WATER SUPPLY & MAINTENANCE DIVISION P.H.E DIRECTORATE, KALIMPONG FROM 01/07/2024 TO 30/09/2024 (3 MONTHS). Assistant Engineer I Junior Engineer III ORD/000012/2024-2025 978/NKWSMD 18/06/2024 90 NIM TSHERING LEPCHA 6.36 0.00 0 0
2 DARJEELING Rangli Rangliot Neorakhola W/S & Mtc.Div. CHEGRA KHASMAHAL Piped Water Supply Scheme , SM/16141 New WATER SUPPLY SCHEME FOR CHEGRA KHASMAHAL PIPED WATER SUPPLY SCHEME IN RANGLI RANGLIOT BLOCK UNDER DARJEELING DISTRICT. ORD/000034/2023-2024 184/NKWSMD 04/05/2023 180 GREEN VALLEY CONSTRUCTION 323.03 74.11 22.94 50
3 DARJEELING Rangli Rangliot Neorakhola W/S & Mtc.Div. CHEGRA KHASMAHAL Piped Water Supply Scheme , SM/16141 New (CONTINUATION) ADDITIONAL ENGAGEMENT OF 01 (ONE) NUMBER COMPUTER OPERATOR (GRADUATE WITH CERTIFICATE IN COMPUTER APPLICATION) FOR THE WORKS RELATED TO JAL JEEVAN MISSION / JAL SWAPNO AT THE OFFICE OF THE SUPERINTENDING ENGINEER, GTA-CIRCLE, PUBLIC HEALTH ENGINEERING DIRECTORATE FROM 01.09.2024 TO 31.10.2024. Assistant Engineer II Junior Engineer I ORD/000103/2024-2025 1537/NKWSMD 30/08/2024 60 QRT SECURITY AND MANPOWER SERVICE 0.39 0.00 0 0
4 DARJEELING Rangli Rangliot Neorakhola W/S & Mtc.Div. CHEGRA KHASMAHAL Piped Water Supply Scheme , SM/16141 New Material Requisition To Resource Division RTOR000010/2023-2024 202/NKWSMD 10/05/2023 Resource Division 1.46 0.00 0 0
Total 331.25 74.11 22.37