Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Block
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted System Order No.
System Order Number
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
2 9.53 6.39 67.05  
1 DARJEELING Neorakhola W/S & Mtc.Div. Providing Functional Household Tap Connection under Jal Jeevan Mission and Jal Swapno Programme for Piped Water Supply Scheme for Bagmara Busty under Kurseong-Sub Division, PHED, GTA , SM/11335 Retrofitting Providing Functional household Tap connection under JJM & JSP Programme including Retrofitting work for PWS scheme for Bagmara Mahanadi GP Block - Kurseong Block. ORD/000216/2022-2023 1110/NKWSMD 05/08/2022 60 MS. SURYA I PVT. LTD COMPANY 9.17 6.39 69.68 0
2 DARJEELING Neorakhola W/S & Mtc.Div. Providing Functional Household Tap Connection under Jal Jeevan Mission and Jal Swapno Programme for Piped Water Supply Scheme for Bagmara Busty under Kurseong-Sub Division, PHED, GTA , SM/11335 Retrofitting Material Requisition To Resource Division RTOR000070/2022-2023 1314/NKWSMD 09/09/2022 Resource Division 0.36 0.00 0 0
Total 9.52 6.39 67.07