Sl No. | District
As per Census (2011)
|
Block
As per Census (2011)
|
Division
Working Divisions
|
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
|
Scheme Category
Category of Scheme as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Name of AE entrusted | Name of JE entrusted | System Order No.
System Order Number
|
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
|
WO Date
Date of Issuance of Work Order
|
Days of Completion
Target Days for Work Completion as per PHED-MIS
|
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
|
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
|
Payment
Amount of Payment made for this Work Order as per PHED-MIS
|
Payment %
Percentage of Payment made for this Work Order as per PHED-MIS
|
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
|
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | 20.72 | 7.86 | 37.93 | ||||||||||||||
1 | DARJEELING | Neorakhola W/S & Mtc.Div. | Providing Functional Household Tap Connection with distribution pipeline retroffting for Piped water supply scheme at Ramam Forest Village , SM/10764 | Retrofitting | Providing Functional household tap connection under JJM & JSP Programme for PWS Scheme Raman Forest Village Source mahabir Jhora Gram Panchyat -Srikhola, Block Darjeeling - Pullbazaar. TSM No. 009295 SM Code-SM/08925 | ORD/000029/2022-2023 | 492/NKWSMD | 24/05/2022 | 60 | NIMA SHERPA | 20.35 | 7.86 | 38.62 | 0 | |||
2 | DARJEELING | Neorakhola W/S & Mtc.Div. | Providing Functional Household Tap Connection with distribution pipeline retroffting for Piped water supply scheme at Ramam Forest Village , SM/10764 | Retrofitting | Material Requisition To Resource Division | RTOR000036/2022-2023 | 1263/NKWSMD | 05/09/2022 | Resource Division | 0.37 | 0.00 | 0 | 0 | ||||
Total | 20.72 | 7.86 | 37.93 |