Sl. No. | Division
Working Divisions
|
System Order No
System generated Order No. for the Work Order as per PHED-MIS
|
Order Date
Date of Issuance of the Work Order as per PHED-MIS
|
Memo Number
Memo no. for Work Order Provided by the Divisions as per PHED-MIS
|
Vendor Name
Vendor Appointed Against this Work Order as per PHED-MIS
|
Work Name
Name of the Work as per the Issued Work Order
|
Order Value
Value of Work as mentioned in the Work Order
|
---|---|---|---|---|---|---|---|
12 | 485.64 | ||||||
1 | Alipore Division | ORD/000746/2024-2025 | 05/11/2024 | 4413/AD | G.B. CONSTRUCTION (TW) | Sinking of 250mm x 150mm dia. 360 mtr. deep Tubewell by Direct Rotary Rig Method using P.V.C pipe and pre-packed Resin Bonded Gravel Filter at Kanthalberia W/S Scheme, Block - Basanti under Canning Sub Division of Alipore Division, PHE Dte. (Tube well no. | 19.68 |
2 | Alipore Division | ORD/001224/2024-2025 | 13/12/2024 | 5182/AD | M/S KHAJABABA ENTERPRISE | Construction of 400 m³ capacity R.C.C OHR (based on Departmental Design & Drawing) with 20 mtr. staging height including Geo- Technical investigation, foundation, pipeline connection and cost of pipes, specials etc. for augmentation of Bhaleya piped wate | 133.61 |
3 | Alipore Division | ORD/000535/2024-2025 | 12/09/2024 | 3709/AD | M/S KHAJABABA ENTERPRISE | Construction of 1 (one) no. switch room cum chlorine room (4.88m x 3.66m) including Sanitary arrangement as per departmental drawing at the site for the Augmentation of Sabek Mahisahara & Adjoining Mouzas (Chunpuri) W/S Scheme, Block - Canning-II under C | 6.97 |
4 | Alipore Division | ORD/000485/2024-2025 | 02/09/2024 | 3544/AD | JYOTY SOLAR POWER | Laying pipeline to connect the uncovered area at Purba Radhanagar (Zone-I) W/S Scheme, Block - Gosaba, under Canning Sub-Division of Alipore Division, P.H.E.Dte. | 27.78 |
5 | Alipore Division | ORD/000511/2024-2025 | 24/06/2024 | 2720/AD | BHUMI FOUNDATION | Wall writing of IEC messages along with logo pictures etc. of multiple colour as will be supplied by the PHE Dte. on smooth wall surface at Falta and Diamond -I block under Alipore Division, PHE Dte. | 3.24 |
6 | Alipore Division | ORD/000822/2024-2025 | 11/11/2024 | 4504/AD | M/S PARAMESWAR CHOWDHURY | Balance works under the Augmentation scheme of Zone-II at Falta block for providing balance pipe lying works, House Hold Tap connection, road restoration works etc.under Mega Surface Water Based Water Supply Scheme for Falta- Mathurapur, District South 24 | 80.38 |
7 | Alipore Division | ORD/001066/2024-2025 | 05/12/2024 | 5003/AD | M/S KHAJABABA ENTERPRISE | Construction of boundary wall and Land development for Tube Well no 3 Site for Ground Water Based of Bibir Abad Piped Water Supply Scheme, Block - Canning- II under Canning Sub-Division of Alipore Division, PHE Dte. | 10.40 |
8 | Alipore Division | ORD/000545/2024-2025 | 12/09/2024 | 3716/AD | I.S. ENTERPRISE | Laying of additional pipe line and other allied works at Bipradaspur W/S Scheme, Block-Gosaba under Canning Sub-Division of Alipore Division, P.H.E. Dte. | 76.62 |
9 | Alipore Division | ORD/000514/2024-2025 | 24/06/2024 | 2721/AD | BHUMI FOUNDATION | Wall writing of IEC messages along with logo pictures etc. of multiple colour as will be supplied by the PHE Dte. on smooth wall surface at Kulpi and Diamond Harbour -II block under Alipore Division, PHE Dte. | 3.40 |
10 | Alipore Division | ORD/000658/2024-2025 | 23/10/2024 | 4204/AD | R.S.CONSTRUCTION CO. | Laying distribution system of piped water supply at Zone- X of Mathurapur - I Block in connection with Jal Jeevan Mission (JJM) for Mega Surface water based water supply scheme for Falta-Mathurapur, District South 24 Parganas under Raidighi Sub-Division | 38.62 |
11 | Alipore Division | ORD/000457/2024-2025 | 21/08/2024 | 3415/AD | M/S KHAJABABA ENTERPRISE | Construction of boundary wall along with Land Development, Plinth Protection and Approach Road for Pump House at 4th Tubewell Site for Achintyanagar W/S scheme, Block : Pathar Pratima under JJM of Kakdwip Sub-Division under Alipore Division, P.H.E. Dte. ( | 9.67 |
12 | Alipore Division | ORD/000442/2024-2025 | 25/07/2024 | 3077/AD | MAA LAXMI ENTERPRISE | Construction, placing and fixing of FHTC platform at every individual beneficiary, pump connections, pile and pile cap for OHR etc at Indraprastha PWSS, Block -Pathar Pratima for implementation of JJM under Kakdwip Sub-Division of Alipore Division, P.H. | 75.28 |
Total | 485.64 |