1 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting Chitnan Water Supply Scheme |
|
|
W/120 |
20/07/2021 |
0 |
ASHOKE GHOSH AND BROTHERS |
15.46 |
0.00 |
0 |
2 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting Chitnan Water Supply Scheme |
|
|
|
19/04/2021 |
0 |
JAHANGIR ALAM |
23.87 |
0.00 |
0 |
3 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting Chitnan |
|
|
|
03/06/2021 |
0 |
S.N ENTERPRISE |
26.88 |
0.00 |
0 |
4 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting Chitnan Water Supply scheme |
|
|
W/170 |
09/08/2021 |
0 |
PRASANTA SANA |
19.78 |
0.00 |
0 |
5 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting Chitnan |
|
|
W/171 |
09/08/2021 |
0 |
BOSE AND CO. |
26.83 |
0.00 |
0 |
6 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block under Howrah Division, PHE Dte. (Part-B) [Beral Mouza] [Number of FHTC to be provided (Approx) : 387] |
AE/Ulu |
JE/USD |
45/HD |
05/01/2021 |
30 |
MS ASOKE GHOSH AND BROTHERS |
4.21 |
0.00 |
0 |
7 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Construction of Bounadry wall Chitnan Water supply scheme |
|
|
BP-2022-23-71 |
14/06/2022 |
0 |
M/S SARADA UDYOG |
2.14 |
0.00 |
0 |
8 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Construction of 35 nos stand post at in various place of Chitnan Water Supply scheme in Uluberia Sub-Division, under Howrah Division, P.H.E. Dte. (Part-I) |
|
|
BP-2021-22-339 |
17/02/2022 |
0 |
ANUP PAUL |
3.28 |
0.00 |
0 |
9 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block under Howrah Division, PHE Dte. (Part-C) [Mirgram Mouza] [Number of FHTC to be provided (Approx) : 415] |
|
|
BP-2021-22-472 |
30/03/2022 |
0 |
PRASANTA SANA |
4.79 |
0.00 |
0 |
10 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Work Order for Riverine effect over Construction of 400 m3 capacity and 20 mtr staging height RCC Over Head Reservoir including pile foundation & delivery inlet & outlet and overflow pipe connection and allied works as per departmental drawing (DRG No. ¿ PC-I/OHR/11/2012) at Chitnan water supply scheme under Uluberia Sub-Division, under Howrah Division PHE Dte |
|
|
|
20/07/2022 |
0 |
S.N ENTERPRISE |
3.52 |
0.00 |
0 |
11 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Construction of 28 nos stand post at in various place of Chitnan Water Supply scheme in Uluberia Sub-Division, under Howrah Division, P.H.E. Dte. (Part-II) |
|
|
BP-2021-22-338 |
17/02/2022 |
0 |
ANUP PAUL |
2.63 |
0.00 |
0 |
12 |
HOWRAH |
Howrah Division |
Retrofitting work for providing Functional Household Tap Connection(FHTC) from existing distribution system at Chitnan Piped Water Supply Scheme under Amta-II Block , SM/07395 |
Retrofitting |
Work Order for Riverine effect over Construction of 400 m3 capacity and 20 mtr staging height RCC Over Head Reservoir including pile foundation & delivery inlet & outlet and overflow pipe connection and allied works as per departmental drawing (DRG No. ¿ PC-I/OHR/11/2012) at Chitnan water supply scheme under Uluberia Sub-Division, under Howrah Division PHE Dte |
AE/Ulu |
JE/USD |
160/HD |
25/01/2022 |
45 |
S.N ENTERPRISE |
4.55 |
4.55 |
0 |