Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 12 of 12 entries
Sl No.District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedWO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12 704.910 
Sl No.
District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
12
704.91
0
 
Total
704.91
0.00
 
1 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Material Requisition To Resource Division 1962/BWD 25/04/2023 0 Resource Division 20.38 0.00 0
2 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Material Requisition To Resource Division 2155/BWD 10/05/2023 0 Resource Division 9.61 0.00 0
3 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New New service connection charges for Barakulgachi PWSS TW-2 BP-2023-24-108 09/08/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 5.73 0.00 0
4 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New New service connection charges for Bara Kulgachi PWSS TW-1 BP-2023-24-131 22/08/2023 0 WEST BENGAL STATE ELECTRICITY DISTRIBUTION CO. LTD. (WBSEDCL) 3.92 0.00 0
5 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New BARA KULGACHHI Piped Water Supply Scheme with sinking of Tube-well, LDS, Rising Main, FHTC, Construction of 300 cum capacity RCC OHR with 20.0 mtr. with Staging height including soil investigation & construction of switch rooms & boundary walls with gates and land development, drain and internal pathway at different TW site under KATWA -II Block, District:- Purba-Bardhaman [NEW SCHEME] Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE 775/BWD 24/02/2023 677 MANASH GHOSH 557.58 0.00 73
6 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Installation of two tank chlorination system, Yard lighting arrangement & allied works at Mulgram & others water supply scheme under Katwa-II Block under Central Mechanical Division, P.H.E. Dte., Dist.- Purba Bardhaman. ASSISTANT ENGINEER Junior Engineer 2409/CMD 02/08/2024 90 DUTTA ENTERPRISE 4.57 0.00 0
7 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Supply & Installation of Submersible Pumping Machinery, Voltage Stabilizer, Chlorination System and Internal House Wiring for Tube well No.-1 & 2 at BARAKULGACHHI Water Supply Scheme [ Block- KATWA-2] under CMD, PHE Dte., Dist.- Purba-Bardhaman. Driller In-Charge Junior Engineer 3173/CMD 26/07/2023 30 GOENKA ENTERPRISE 23.79 0.00 90
8 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Supply, delivery, installation & hand hold demonstration of different equipments / machineries to test HDPE pipes as per IS: 4984-2016 at the pipe testing laboratory at Nababhat under Burdwan Division, PHE. Dte._2ND CALL AE(HQs) J.E. 1 BURDWAN 907/BWD 04/03/2024 30 MANASH GHOSH 3.83 0.00 100
9 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Material Requisition To Resource Division 331/BWD 24/01/2024 0 Resource Division 16.79 0.00 0
10 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Providing of balance FHTC and other allied works at Barakulgachhi, Chhoto Kulgachhi and Garagachha under the command area of BARAKULGACHI PWSS (SM/14079) in order to declare Sajal Gram, under Katwa-II Block under Katwa Sub-Division, PHE Dte. Assistant Engineer 982/BWD 13/03/2025 21 MANASH GHOSH 9.51 0.00 0
11 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Road crossing through metal/Concrete road by Jack Push Method for Barakulgachhi PWSS(SM/14079) of Katwa-II Block Development Block under Katwa Sub-Division within Burdwan Division PHE Dte. Assistant Engineer JUNIOR ENGINEER KATWA SUB-DIVISION PHE DTE 1297/BWD 25/04/2025 30 MONDAL & CO. 43.65 0.00 100
12 PURBA BARDHAMAN Burdwan Division BARA KULGACHHI PIPED WATER SUPPLY SCHEME , SM/14079 New Material Requisition To Resource Division 382/BWD 17/01/2025 0 Resource Division 5.55 0.00 0
Total 704.910.00 
Showing 1 to 12 of 12 entries