Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 5 of 5 entries
Sl No.District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedWO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 543.354.19 
Sl No.
District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5
543.35
4.19
 
Total
543.35
4.19
 
1 BIRBHUM Birbhum Division BALIARA PIPED WATER SUPPLY SCHEME , SM/14847 New Different works related to water supply scheme at BALIARA & its adjoining mouzas water supply scheme within NANOOR Block including supply of all labour & materials under BIRBHUM Division, PHE Dte. AE JE4 1426/BHM 25/04/2023 275 M/S REBATI SANKAR SINHA 378.55 0.00 0
2 BIRBHUM Birbhum Division BALIARA PIPED WATER SUPPLY SCHEME , SM/14847 New Continuation Work Order for "Preparation & Submission of Detail Project Report (DPR) for BALIARA Piped Water Supply Scheme under Nanoor Development Block within Bolpur Sub-Division under Birbhum Division, PHE Dte.". AE JE4 103/BSD 16/03/2022 90 RADIANT 4.19 4.19 100
3 BIRBHUM Birbhum Division BALIARA PIPED WATER SUPPLY SCHEME , SM/14847 New Material Requisition To Resource Division 1559/BHM 26/04/2023 0 Resource Division 22.71 0.00 0
4 BIRBHUM Birbhum Division BALIARA PIPED WATER SUPPLY SCHEME , SM/14847 New Construction of Tube Well (300 MM x 200 MM x Depth 450 Mtr) for Baliara WSS (TW No I and II), Block- Nanoor, in Birbhum District under Bolpur Mechanical Division, P.H.E Dte. Assistant Engineer Junior Engineer 4531/BOL.MD 20/12/2024 120 SATYAJIT GHOSH 75.08 0.00 0
5 BIRBHUM Birbhum Division BALIARA PIPED WATER SUPPLY SCHEME , SM/14847 New Construction of Big Diameter Tube-Well by Deploying of Suitable Capacity Drilling Rig (Direct Rotary, Reverse Rotary, Odex Method) at Different Districts for Different Water Supply Schemes Including Procurement & Installation Pumping Machinery with All Allied Accessories at the Above Constructed Tube-Wells Under JJM Program throughout the State of West Bengal. (2ed call of NIET 25 of 2022-23) Assistant Engineer,Driller In Charge Junior Engineer 1415/CDD 21/09/2023 304 JHARGRAM SPV PRIVATE LIMITED 62.82 0.00 11
Total 543.354.19 
Showing 1 to 5 of 5 entries