Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Showing 1 to 6 of 6 entries
Sl No.District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrustedName of JE entrustedWO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6 119.4816.02 
Sl No.
District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted
Name of JE entrusted
WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
6
119.48
16.02
 
Total
119.48
16.03
 
1 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Preparation of DPR for drinking water supply scheme to facilitate 4(Four)Nos. Augmentation Scheme and 1(One) No. New PWSS (List Enclosed) Uncovered mouzas under Uttar Dinajpur District which includes Route survey using DGPS/Drone/Total Station etc. & all related field work for technical data collection, Household Survey using PHED developed mobile application, Preparation and supply of Geo reference drawing / layout plan of the zone-wise Command area of water distribution and transmission Pipeline network of the schemes showing all requisite features, design of Pipeline Network. Design (if necessary), drawing & estimation of all necessary structures, Preparation & Submission of DPR booklets & Bid Document ( in both hard and soft copies) including Preparation of Booklet for SLSSC for individual PWSS, all complete in consultation with the EIC under Raiganj Division P.H.E. Dte. Assistant Engineer RSD 2226/RD/PHE 31/07/2023 15 RADIANT 1.10 1.10 100
2 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Material Requisition To Resource Division 1106/RD/PHE 20/04/2023 0 Resource Division 6.34 0.00 0
3 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Supply, installation ,commissioning and trial operation of electro-mechanical components at T/W no.III of Source augmentation of Kaliganj (Bangar Village) Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/018636) Assistant Engineer - I Junior Engineer-02 2753/MLMD 14/08/2023 867 M/S. MAYUKH BHADURI 7.16 5.83 81
4 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Augmentation of Kaliganj (Bangar) and it's adjoining mouzas Pipe Water Supply Scheme at Itahar Block of Uttar Dinajpur District under Raiganj Division.(Sinking of Tube Well, Laying of Rising Main, Laying Distribution pipe line, Providing Functional house Hold Tap Connections, Pump House) Assistant Engineer HQ,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer RWS HQ,Junior Engineer, RSD ,Junior Engineer, RWS 884/RD/PHE 27/03/2023 899 BHOLA PAUL 78.26 9.09 30
5 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Construction of Approach Road, Laying of Pipe Line, FHTC And Other Allied Works of Kaliganj(Bangar) Pwss Within Itahar Block Under Raiganj Division P.H.E. Dte., Raiganj, Uttar Dinajpur. Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD Junior Engineer RWS HQ 3560/RD/PHE 05/12/2024 91 TAPAN KUMAR MAJUMDER NAMEDUTTA@GMAIL.COM 18.03 0.00 0
6 UTTAR DINAJPUR Raiganj Division Augmentation of Kaliganj (Bangar village) Piped Water Supply Scheme at Itahar block under Uttar Dinajpur District. , SM/17740 Augmentation Quotation for new service connection at Augmentation of Kaliganj (Bangar) (Itahar ccc) in the district of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (SM/17740) 23/05/2025 0 W.B.S.E.D.C.LTD 8.59 0.00 0
Total 119.4816.03 
Showing 1 to 6 of 6 entries