Work Order Tracking
Status Report on the Progress and Achievement at Individual Work Order Level

Rs. in Lakh
Sl No. District
As per Census (2011)
Division
Working Divisions
Scheme
Schemes for which Work Order has been issued as per PHED-MIS
Scheme Category
Category of Scheme as per PHED-MIS
Work Name
Name of the Work as per the Issued Work Order
Name of AE entrusted Name of JE entrusted WO Number
Manual No. Provided by the Divisions as per PHED-MIS
WO Date
Date of Issuance of Work Order
Days of Completion
Target Days for Work Completion as per PHED-MIS
Agency Name
Agency Appointed Against this Work Order as per PHED-MIS
Work Value
Value of Work as mentioned in the Work Order as per PHED-MIS
Payment
Amount of Payment made for this Work Order as per PHED-MIS
Physical Progress %
Achievement of Physical Progress of the work under this Work Order as per PHED-MIS
5 704.03 309.64  
1 UTTAR DINAJPUR Raiganj Division PUAR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13550 New Material Requisition To Resource Division 984/RD/PHE 30/03/2023 0 Resource Division 30.70 0.00 0
2 UTTAR DINAJPUR Raiganj Division PUAR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13550 New Supply, installation, commissioning and trial operation of electro-mechanical components at T/W no. I & II and making compound lighting arrangement at T/W no. I of Puar Water Supply Scheme in the District of Uttar Dinajpur under Malda Mechanical Division, PHE Dte. (TSM/015848) Assistant Engineer - I Junior Engineer-02 2524/MLMD 04/08/2023 840 MERCURY ENGINEERING COMPANY. 29.75 22.42 75
3 UTTAR DINAJPUR Raiganj Division PUAR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13550 New Continuation work- Hiring of Inspection vehicle (Diesel driven) for official use of Assistant Engineer-I under office of the Executive Engineer, Malda Mechanical Division, P.H.E. Dte Assistant Engineer - I Junior Engineer-04 1670/MLMD 25/06/2024 62 RAMCHANDRA BASAK 0.78 0.77 100
4 UTTAR DINAJPUR Raiganj Division PUAR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13550 New Additional pipeline and other ancillary works at Puar piped water Supply Scheme Under Islampur SubDivision under Raiganj Division,P.H.E Dte. Assistant Engineer HQ,Assistant Engineer ISD,Assistant Engineer RSD,Assistant Engineer RWS SD 2341/RD/PHE 22/08/2025 45 MILAN GHOSH 32.63 0.00 0
5 UTTAR DINAJPUR Raiganj Division PUAR PIPED WATER SUPPLY SCHEME AT GOALPOKHAR-II BLOCK UNDER UTTAR DINAJPUR DISTRICT. , SM/13550 New Sinking of Tube Well, laying of rising main & distribution system, providing FHTC ,Construction of Over Head Reservoir over Pile / Raft Foundation including subsoil investigation, construction of Pump House, Chlorine room, Boundary Wall & Approach Road and allied works for 25 nos. Piped water supply Schemes within GOALPOKHAR-II Dev. Block of Uttar Dinajpur District under Raiganj Division ,PHE Dte. Assistant Engineer ISD JUNIOR ENGINEER,Junior Engineer, ISD 2590/RD/PHE 11/09/2023 810 M/S GHOSH AND CO. 610.17 286.45 35
Total 704.02 309.65